As I've said a few times, they are currently on plan for October, yet the contractual hand-over is at the latest December; after this, LOR occur penalties.That's always been the brief given to the media.
Heard on good authority it's ahead of schedule, Oct or maybe even September completion (including testing events)
Would be a monumental mistake if they don't use it for close to 12 months for the men's 1st team .
I know we've made some complete f-ups in the past but doing that would top the lot
The club is planning on the October to November handover, a two-month transition period and then playing games from mid to late January onwards.